Cianbro performed the above-grade expansion of the 138 kV substation including the removal of existing equipment and installing new switches, bus CCVT, transformer, and arrestors. Cianbro upgraded the 69 kV section of the substation including a new CCVT. For the 34 kV portion of the project, Cianbro removed switches, bus, station service transformers, and cabinets, and installed new switches, bus, station service transformer, cabinets, and control building.
The project team completed all work for the substation expansion while working within an energized facility, including trenching and excavations for below-grade installations. Additionally, the project team coordinated partial outages required to create clearance for above-grade work to minimize power interruption.