Scope of Work

Cianbro was the Construction Manager of the state-of-the-art, 510,000-square-foot Poland Spring Water Bottling Plant.

Project Details

  • Managed the construction in two phases
    • Phase I—270,000 square feet of bottling and warehouse space and 12,500 square feet of office space
    • Phase II—240,000 square feet of warehouse space
  • Performed constructability reviews
  • Supplied over 2,500 tons of structural steel
  • Erected 1,285 tons of structural steel
  • Placed 510,000 square feet of flat slab concrete
  • Coordinated construction around the installation of process equipment
  • Installed a wet well for PH neutralization system which included cofferdams
  • Self-performed all source water piping including 12,000 feet of 8 inch TIG welded stainless steel pipe and 16,000 feet of 4 inch computerized orbital welded stainless steel pipe