Berlin Cluster Rules 15 kV and 25 kV Transmission Lines

Location:
Berlin, NH
Completed:
2004

Scope of Work

Installation of all High Voltage Utilities for the 25MW Cogeneration Facility Project.

Project Details

  • Installed 15 kV distribution line
  • Installed 25 kV transmission line
  • Installed new air brake switches in sub 3
  • Installed 1200 amp, 25 kV air brake switch for the Cogeneration Facility
  • Installed all site transformers and completed all related work

Lean, Innovative, and Unique Project Solutions

Cianbro removed the existing 4/0 wire and installed a new 795 ACSR without interruption of power so that the facility could remain fully functional.