Lower Bank Bridge Replacement

Location:
Lower Bank, NJ
Completed:
1993

Scope of Work

Cianbro constructed a 1,200 lf, articulating, overhead counterweight, bascule bridge to replace the existing wooden bridge over the Mullica River.

Project Details

  • Demolished the existing bridge
  • Constructed seven piers with concrete piles and pile caps
  • Installed the pre-stressed concrete box beam span superstructure
  • Performed electrical work for the control and power distribution systems
  • Performed mechanical work and installed operating equipment—a primary and two secondary reducers driving a final-drive pinion
  • Replaced bascule span with structural steel framing and deck
  • Installed span lock system
  • Constructed the control house off site—installing it in one piece

Lean, Innovative, and Unique Project Solutions

The Cianbro team successfully managed changing site conditions to install concrete sheet pile bulkheads spanning the east and west approaches.